Attribute it to force majeure.

Can developers halt construction due to the war?

A collapse is brewing in the real estate market. Developers cannot build, investors cannot pay. Is the war in Ukraine considered a force majeure circumstance that exempts construction companies from fulfilling their obligations to investors?

Those who invested funds in a new residential building before the start of the war face, at best, a significant delay in commissioning, and at the worst, the loss of their investments. After all, even in Kyiv, from which the Armed Forces of Ukraine pushed back enemy forces back in late March, about a third of residential complexes under construction remain frozen since late February, as Focus writes in its new review “Money now, apartment later. Can home buyers get their money back for a long-delayed construction.”

Maksym Koldoba, an attorney and partner at the ASA GROUP law firm, notes that in the current situation, many developers justify delaying the deadlines for putting housing into operation by citing the Letter of the Ukrainian Chamber of Commerce and Industry dated February 28, 2022, No. 2024/02.0-7.1, which recognizes Russia’s military aggression against Ukraine as a force majeure circumstance.

However, the Focus interviewee draws investors’ attention to the fact that the existence of force majeure circumstances exempts from liability for delayed performance of obligations in the form of fines and penalties for the duration of such circumstances. At the same time, no force majeure, which developers may speculate on, relieves them of the obligation to build the real estate object, put it into operation, and transfer the purchased apartments to the investors.

READ OTHER NEWS

Insights from Ihor Mlechko on corporate structuring, tax security, and dispute resolution.

Media about us