ASA Group Wins Contract Dispute for a Supplier, Recovering More Than UAH 2 Million for Unpaid Construction Materials

 

A property developer ordered construction materials worth nearly UAH 2 million for a construction project.

The supplier, an ASA Group client, delivered all of the materials and requested payment. The customer then stopped responding to emails, calls, and messages, failed to pay, and ignored even a warning that legal proceedings would follow.

With ASA Group representing its interests, the supplier went to court seeking recovery of the full outstanding amount together with contractual penalties for late payment.

During preparation for the case, the team identified a significant evidentiary risk: the customer had not signed some of the delivery documents, while several goods transport waybills bore only the customer’s company seal.

ASA Group’s Legal Position

  • The customer had affixed its company seal to some of the goods transport waybills acknowledging receipt of the goods, thereby confirming acceptance of the delivery.
  • The company seal was sufficient to authenticate those documents. Because the customer had never reported the seal lost or misused, there were grounds to conclude that the goods had been accepted by an authorized representative of the customer.
  • The remaining goods transport waybills had not been signed or stamped by the customer.
  • The supplier sent those waybills to the customer through the M.E.Doc electronic document system. The customer received them but neither provided a reasoned refusal to sign the delivery documents nor raised any objections to them.
  • Based on the goods transport waybills, the supplier issued tax invoices and registered them in the Unified Register of Tax Invoices.
  • The customer subsequently filed VAT returns with the State Tax Service and claimed input VAT on the basis of those tax invoices, thereby effectively confirming that the underlying supply transactions had taken place.

Outcome

Thanks to the ASA Group team’s legal arguments, documentary evidence, and litigation strategy, the court ruled in the client’s favor and confirmed that the deliveries had been duly made.

The customer was ultimately required to pay the overdue amount for the supplied materials and reimburse an additional UAH 72,000 in legal fees incurred for ASA Group’s representation of the supplier.