UAH 5.5 Million Fine Without Fault: How ASA Group Protected a Road Construction Company from Automatic Tax Sanctions

A concerning trend has emerged in tax enforcement: an inspector no longer needs to visit a company’s premises to identify grounds for a multi-million-hryvnia penalty. A comparison of figures in an electronic database may be enough for the system to flag a violation automatically. Yet a discrepancy in reporting does not necessarily mean that the taxpayer is at fault.

An ASA Group client – a major road construction company whose principal customer is the state – found itself in exactly this position. Delayed state payments for completed works and a shortfall in the company’s VAT registration limit caused technical delays in tax payments. The State Tax Service did not take those circumstances into account and conducted a desk audit, identifying late payments under six tax returns for the period from 2022 to 2024.

The authority’s approach was purely mathematical: the inspector compared each statutory payment deadline with the date on which the corresponding funds were actually paid. Because the dates did not match, the State Tax Service automatically imposed penalties under Article 124.1 of the Tax Code of Ukraine – 5% or 10%, depending on the length of the delay. The total penalties exceeded UAH 5.5 million, against outstanding tax liabilities of more than UAH 60 million.

A distinctive feature of the case was that the tax authority relied exclusively on data from the Tax Block information and communication system, while disregarding the real causes of the delays, including the funding model for state road construction and the effects of martial law.

The Foundation of ASA Group’s Winning Strategy

The ASA Group team developed a comprehensive defense strategy and demonstrated a number of systemic errors and procedural violations:

  1. The company was penalized automatically. A taxpayer is presumed to act in good faith, while the state bears the burden of proving that a penalty is lawful. Here, the State Tax Service relied on assumptions and did not establish culpable conduct by the company.
  2. The State Tax Service failed to prove fault. Since 2021, the relevant rules require the authority to establish that the taxpayer had a genuine ability to pay on time and nevertheless failed to do so. Instead, the tax authority effectively shifted the burden of proof to the business and produced no evidence that sufficient funds were available in the company’s accounts while it deliberately withheld payment.
  3. The State Tax Service relied on an inadequate evidentiary source. Data displayed in the Tax Block system are not primary accounting documents and cannot, by themselves, establish or disprove fault. Without examining the taxpayer’s bank statements and the underlying circumstances, the authority’s conclusions were unsupported.
  4. The State Tax Service did not first request an explanation from the taxpayer. This deprived the company of the opportunity to explain the reasons for the delay, including payment delays by the State Treasury – a particularly important factor in the road-construction sector.
  5. Questions of reasonableness, good faith, and due care fall outside the proper scope of a desk audit, which is limited to checking reported figures and data. A substantive examination of the reasons for a payment delay requires a documentary audit; electronic-system data alone cannot establish those circumstances.
  6. The audit report contained virtually no substantive analysis of the materials required by law. It reproduced figures from the database without examining the underlying facts, making it an inadequate basis for imposing a penalty.
  7. The tax authority treated Article 124 of the Tax Code as if it imposed automatic liability for every late payment regardless of the surrounding circumstances. In doing so, it disregarded the statutory requirement to establish fault and attempted to apply an outdated enforcement approach under the current legal framework.

Outcome and Benefits for the Client

The court agreed with ASA Group that a business cannot be penalized solely because a payment was late without examining the reasons for the delay and establishing fault.

Thanks to the work of ASA Group Managing Partner Ihor Mlechko and attorney Natalia Pysmenna, the UAH 5.5 million penalty was cancelled. The company also preserved more than UAH 60 million in liquidity, taking into account the underlying tax liabilities, enabling it to continue performing state road-construction contracts and paying the salaries of hundreds of employees.