How can investments in stalled construction projects be protected?

Maksym Koldoba shares his experience in lawmaking at the VIII Business & Legal Real Estate Forum.

Stalled and abandoned buildings are far from uncommon in Ukraine’s real estate market.

Investors have often been left to deal on their own with the consequences of projects associated with Ukrbud, Arkada, Voitsekhovskyi and other developers.

Ordinary Ukrainians do not have sufficient legal tools to protect themselves from unscrupulous developers who accepted their money but failed to complete construction.

However, the state is already working on a mechanism intended to balance investors’ interests and help them complete their homes.

ASA Group became a partner of the VIII Business & Legal Real Estate Forum — a leading platform organized by Yurydychna Praktyka that traditionally brings together top real estate and construction experts and engages government representatives in a substantive discussion of practical steps needed to improve the market.

Earlier, Maksym Koldoba personally joined the working group that developed a draft law to support investors in unfinished construction projects. As a speaker in Session 3 of the Forum, Maksym therefore shared his experience of working on initiatives designed to protect creditors’ rights, as well as practical cases in which creditors were able to complete construction without involving the original developers.

During his presentation, Maksym explained how the reform is intended to help investors in stalled construction projects.

Analysis of construction sector problems by LUN

 

  • 3,200 project phases were due to be commissioned between 2022 and 2025.
  • 43% were commissioned: 13% on time and 30% with delays ranging from six months to two years.
  • 57% were not commissioned at all, including 26% postponed indefinitely.

 

Draft Law “On Assisting Affected Investors”

 

Objective: To create a consistent algorithm of actions for investors and government authorities to identify distressed projects and ensure their completion.

 

Benefits for investors:

  • Ownership rights to the project
  • The right to use the land plot for completion of the project regardless of its previous designated purpose
  • A simplified procedure for obtaining urban-planning conditions and restrictions

  • No infrastructure participation contribution
  • No need to obtain technical conditions again

 

How it will work:

  • Troubled projects would be included in an official list approved by the Cabinet of Ministers.

  • A list of creditors would be compiled for each project on the basis of applications and supporting documents.
  • Investors would create a creditors’ association which:

 

— as a legal entity similar to an association of co-owners, represents the interests of all investors

— applies to the commercial court for recognition of ownership rights to the troubled project, including any unallocated usable floor area

— after obtaining a court decision recognizing ownership rights and receiving the land plot for use, may complete the project independently or through a new developer

 

Potential challenges:

  • Difficulty proving a claim where payments were made in cash
  • Risk of double sales of property rights and abuse when creditor lists are being formed
  • Lack of a clear mechanism for projects that become troubled after the Cabinet of Ministers has approved the list

 

Practical case study

Completion of an abandoned residential complex belonging to one of Kyiv’s notorious developers.

 

Practical case:

  • Established the NGO “RC XXX”
  • Placed the unfinished construction project on the organization’s balance sheet
  • Obtained the right to use the land plot
  • Negotiated with a potential developer on completing construction using the unallocated square metres to finance the work

 

Why completion has not yet been achieved:

  • There is no accurate information on the amount of sold and unallocated floor area — property rights were sold in a way that resulted in numerous “phantom” investors.

  • The developer cannot properly assess the project economics.